Dept. of Trans. PROGRESS Serial No. Contract No. 21-146-10-26 01-0K9004 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 15% Location: Federal Project: 01-HUM-101-78.0/79.1 NONE Progress payment No. 005 Payment period ending: 05-20-21 WAHLUND CONSTRUCTION INC PO BOX 6486 EUREKA CA 95502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 239,975.96 23,122.75 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 239,975.96 23,122.75 5. Mobilization 6. Total Work Completed 239,975.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 239,975.96 23,122.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,122.75