Dept. of Trans. PROGRESS Serial No. Contract No. 21-207-14-09 01-0L0704 PROGRESS PAYMENT VOUCHER %complete: %time: 5% 100% Location: Federal Project: 01-DN-101-42.0/42.0 NONE Progress payment No. 001 Payment period ending: 06-20-21 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 15,235.26 15,235.26 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 15,235.26 15,235.26 5. Mobilization 6. Total Work Completed 15,235.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,235.26 15,235.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,235.26