Dept. of Trans. PROGRESS Serial No. Contract No. 23-296-14-57 01-0L3904 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 01-HUM-101-865.0/86.7 NONE Progress payment No. 023 Payment period ending: 10-20-23 WAHLUND CONSTRUCTION INC PO BOX 6486 EUREKA CA 95502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 5,950,245.91 9,080.25 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 5,950,245.91 9,080.25 5. Mobilization 6. Total Work Completed 5,950,245.91 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,950,245.91 9,080.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,080.25