Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-06-46 01-0L9604 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 54% Location: Federal Project: 01-VAR NONE Progress payment No. 005 Payment period ending: 08-20-25 TPA CONSTRUCTION INC 1770 BOOTH RD ROSEVILLE CA 95747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 892,235.58 329,360.08 2. a. Extra Work 11,223.69 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 903,459.27 329,360.08 5. Mobilization 213,750.00 0.00 6. Total Work Completed 1,117,209.27 7. Deductions -16,812.81 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,100,396.46 329,360.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 329,360.08