Dept. of Trans. PROGRESS Serial No. Contract No. 23-137-11-04 01-0M7904 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 37% Location: Federal Project: 01-LAK-29-125.0/14.5 NONE Progress payment No. 004 Payment period ending: 05-20-23 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 978,041.71 55,551.24 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 978,041.71 55,551.24 5. Mobilization 6. Total Work Completed 978,041.71 7. Deductions -11,000.00 9,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 967,041.71 64,551.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 64,551.24