Dept. of Trans. PROGRESS Serial No. Contract No. 24-114-14-18 01-0P0304 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 25% Location: Federal Project: 01-HUM-101-330.0/34.0 NONE 01-HUM-254-180.0/18.0 Progress payment No. 001 Payment period ending: 04-20-24 PACIFIC EARTHSCAPE 1225 CENTRAL AVE #11 MCKINLEYVILLE CA 95519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 640,651.90 640,651.90 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 640,651.90 640,651.90 5. Mobilization 6. Total Work Completed 640,651.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 640,651.90 640,651.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 640,651.90