Dept. of Trans. PROGRESS Serial No. Contract No. 24-296-09-17 01-0P1704 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 64% Location: Federal Project: 01-MEN-1-749.0/78.0 NONE Progress payment No. 004 Payment period ending: 10-20-24 WYLATTI RESOURCE MANAGEMENT INC PO BOX 575 COVELO CA 95428 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 186,312.59 6,050.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 186,312.59 6,050.00 5. Mobilization 6. Total Work Completed 186,312.59 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 184,312.59 4,050.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,050.00