Dept. of Trans. PROGRESS Serial No. Contract No. 25-205-15-53 01-0Q1004 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 56% Location: Federal Project: 01-MEN-1-418.0/42.5 NONE Progress payment No. 001 Payment period ending: 07-20-25 WYLATTI RESOURCE MANAGEMENT INC PO BOX 575 COVELO CA 95428 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 889,098.61 889,098.61 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 889,098.61 889,098.61 5. Mobilization 6. Total Work Completed 889,098.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 889,098.61 889,098.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 889,098.61