Dept. of Trans. PROGRESS Serial No. Contract No. 01-234-15-43 01-194134 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 36% 01-MEN-20-43.0/44.1 Federal Project: 01-LAK-20-0.0/0.6 NH-L20 Progress payment No. 04 Payment period ending: 08-20-01 PARNUM PAVING INC P O BOX 970 UKIAH CA 95482 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 801,852.83 196,710.10 2.a. Extra Work 82,973.61 32,297.04 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 884,826.44 229,007.14 5. Mobilization 346,750.00 73,000.00 6. Total Work Completed 1,231,576.44 7. Deductions 8. a.Contract Retentions -69,849.61 -4,267.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,161,726.83 297,739.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,739.46