Dept. of Trans. PROGRESS Serial No. Contract No. 13-169-09-44 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 30% 01-MEN-101-R43.1/49.0 Federal Project: NONE Progress payment No. 09 Payment period ending: 06-13-13 DESILVA GATES - FLATIRON WEST, A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,224,595.60 1,141,799.20 2.a. Extra Work 517,008.57 150,810.24 b. Adjustment Comp. -38,350.00 -38,350.00 3. Materials on Hand 1,774,379.37 145,923.37 4. Earned Subject to Retention 5,477,633.54 1,400,182.81 5. Mobilization 5,400,000.00 5,400,000.00 6. Total Work Completed 9,103,254.17 7. Deductions -16,589.27 -1,589.27 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,861,044.27 6,798,593.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,798,593.54