Dept. of Trans. PROGRESS Serial No. Contract No. 13-203-13-10 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 34% 01-MEN-101-R43.1/49.0 Federal Project: NONE Progress payment No. 11 Payment period ending: 07-18-13 DESILVA GATES - FLATIRON WEST, A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,667,383.89 3,442,788.29 2.a. Extra Work 1,234,060.91 431,931.01 b. Adjustment Comp. -250,160.00 -211,810.00 3. Materials on Hand 1,635,148.00 -139,231.37 4. Earned Subject to Retention 9,286,432.80 3,523,677.93 5. Mobilization 5,400,000.00 0.00 6. Total Work Completed 13,051,284.80 7. Deductions -26,589.27 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,659,843.53 3,513,677.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,513,677.93