Dept. of Trans. PROGRESS Serial No. Contract No. 13-263-08-03 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 42% 01-MEN-101-R43.1/49.0 Federal Project: NONE Progress payment No. 13 Payment period ending: 09-17-13 DESILVA GATES - FLATIRON WEST, A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,980,118.02 4,943,095.04 2.a. Extra Work 2,800,714.96 1,347,190.04 b. Adjustment Comp. -281,272.64 4,877.36 3. Materials on Hand 2,663,629.79 1,010,112.60 4. Earned Subject to Retention 22,163,190.13 7,305,275.04 5. Mobilization 10,260,000.00 2,160,000.00 6. Total Work Completed 29,759,560.34 7. Deductions -38,019.62 -635.71 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,385,170.51 9,464,639.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,464,639.33