Dept. of Trans. PROGRESS Serial No. Contract No. 13-296-13-58 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 46% 01-MEN-101-R43.1/49.0 Federal Project: NONE Progress payment No. 14 Payment period ending: 10-17-13 DESILVA GATES - FLATIRON WEST, A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,612,109.42 3,631,991.40 2.a. Extra Work 3,939,378.84 1,138,663.88 b. Adjustment Comp. -288,472.64 -7,200.00 3. Materials on Hand 2,427,081.85 -236,547.94 4. Earned Subject to Retention 26,690,097.47 4,526,907.34 5. Mobilization 10,260,000.00 0.00 6. Total Work Completed 34,523,015.62 7. Deductions -48,019.62 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 36,902,077.85 4,516,907.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,516,907.34