Dept. of Trans. PROGRESS Serial No. Contract No. 13-354-14-54 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 54% 01-MEN-101-R43.1/49.0 Federal Project: NONE Progress payment No. 17 Payment period ending: 12-18-13 DESILVA GATES - FLATIRON WEST, A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,218,917.86 -68,686.45 2.a. Extra Work 4,653,333.60 436,630.32 b. Adjustment Comp. -17,756.86 64,225.97 3. Materials on Hand 3,588,001.00 1,213,190.62 4. Earned Subject to Retention 30,442,495.60 1,645,360.46 5. Mobilization 10,260,000.00 0.00 6. Total Work Completed 37,114,494.60 7. Deductions -48,019.62 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 40,654,475.98 1,645,360.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,645,360.46