Dept. of Trans. PROGRESS Serial No. Contract No. 14-023-10-01 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 58% 01-MEN-101-R43.1/49.0 Federal Project: NONE Progress payment No. 18 Payment period ending: 01-17-14 DESILVA GATES - FLATIRON WEST, A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,254,272.31 35,354.45 2.a. Extra Work 4,790,589.44 137,255.84 b. Adjustment Comp. -17,756.86 0.00 3. Materials on Hand 3,619,104.96 31,103.96 4. Earned Subject to Retention 30,646,209.85 203,714.25 5. Mobilization 10,260,000.00 0.00 6. Total Work Completed 37,287,104.89 7. Deductions -43,019.62 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 40,863,190.23 208,714.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 208,714.25