Dept. of Trans. PROGRESS Serial No. Contract No. 14-300-09-54 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 46% 01-MEN-101-R43.1/49.0 Federal Project: NONE Progress payment No. 28 Payment period ending: 10-20-14 DESILVA GATES - FLATIRON WEST, A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,056,148.71 5,746,977.82 2.a. Extra Work 12,117,400.87 105,097.23 b. Adjustment Comp. 5,330,366.93 471,528.08 3. Materials on Hand 1,978,337.19 146,462.38 4. Earned Subject to Retention 65,482,253.70 6,470,065.51 5. Mobilization 10,800,000.00 0.00 6. Total Work Completed 74,303,916.51 7. Deductions -58,178.55 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 76,224,075.15 6,460,065.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,460,065.51