Dept. of Trans. PROGRESS Serial No. Contract No. 16-083-08-24 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 69% Location: Federal Project: 01-MEN-101-R43.1/49.0 NONE Progress payment No. 048 Payment period ending: 03-20-16 DESILVA GATES - FLATIRON WEST A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 80,927,496.83 536,260.58 2. a. Extra Work 44,703,674.85 329,762.90 b. Adustment Comp. 14,144,062.75 246,834.73 3. Materials on Hand 410,130.34 -12,531.68 4. Earned Subject to Retention 140,185,364.77 1,100,326.53 5. Mobilization 10,800,000.00 0.00 6. Total Work Completed 150,575,234.43 7. Deductions -33,358.57 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 150,952,006.20 1,100,326.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,100,326.53