Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-072-14-08 01-262004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-MEN-101-R43.1/49.0 NONE Progress payment No. 061 Payment period ending: 12-16-16 DESILVA GATES - FLATIRON WEST A JOINT VENTURE 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 90,056,769.45 43,703.00 2. a. Extra Work 54,017,397.52 252,816.32 b. Adustment Comp. 18,457,080.90 55,091.82 3. Materials on Hand 4. Earned Subject to Retention 162,531,247.87 351,611.14 5. Mobilization 10,800,000.00 0.00 6. Total Work Completed 173,331,247.87 7. Deductions -57,180.02 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 173,274,067.85 371,611.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 371,611.14