Dept. of Trans. PROGRESS Serial No. Contract No. 15-042-14-36 01-262024 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 95% Location: Federal Project: 01-MEN-101-45.0/50.8 ACNH-Q101(203) Progress payment No. 007 Payment period ending: 02-06-15 SIERRA VIEW LANDSCAPE, INC. DBA RESTORATION RESOURCES 3888 CINCINNATI AVENUE ROCKLIN, CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 3,078,038.85 63,422.06 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,078,038.85 63,422.06 5. Mobilization 6. Total Work Completed 3,078,038.85 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,078,038.85 63,422.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,422.06