Dept. of Trans. PROGRESS Serial No. Contract No. 18-081-09-02 01-262064 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 40% Location: Federal Project: 01-MEN-101-45.0/50.8 NHP-Q101(266) Progress payment No. 026 Payment period ending: 03-20-18 BORTOLUSSI AND WATKIN INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,063,595.27 60,906.00 2. a. Extra Work 196,997.99 1,762.50 b. Adustment Comp. 159,458.90 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,420,052.16 62,668.50 5. Mobilization 420,000.00 0.00 6. Total Work Completed 3,840,052.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,840,052.16 62,668.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,668.50