Dept. of Trans. PROGRESS Serial No. Contract No. 10-202-10-27 01-290304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 92% 01-HUM-101-57.0/59.1 Federal Project: NONE Progress payment No. 21 Payment period ending: 07-20-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,518,593.63 839,991.52 2.a. Extra Work 450,196.72 6,139.55 b. Adjustment Comp. -138,553.78 0.00 3. Materials on Hand 48,934.88 48,934.88 4. Earned Subject to Retention 12,879,171.45 895,065.95 5. Mobilization 641,777.50 0.00 6. Total Work Completed 13,472,014.07 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -643,958.57 -44,753.29 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,876,990.38 860,312.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 860,312.66