Dept. of Trans. PROGRESS Serial No. Contract No. 10-237-13-58 01-290304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 99% 01-HUM-101-57.0/59.1 Federal Project: NONE Progress payment No. 22 Payment period ending: 08-20-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,173,707.30 655,113.67 2.a. Extra Work 586,074.46 135,877.74 b. Adjustment Comp. -138,553.78 0.00 3. Materials on Hand 0.00 -48,934.88 4. Earned Subject to Retention 13,621,227.98 742,056.53 5. Mobilization 641,777.50 0.00 6. Total Work Completed 14,263,005.48 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions -681,061.40 -37,102.83 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,576,944.08 699,953.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 699,953.70