Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 06-125-10-57 01-293014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 55% 01-MEN-101-10.7/ .0 Federal Project: ACNH-Q101(66) Progress payment No. 13 Payment period ending: 04-20-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,577,303.50 24,685.20 2.a. Extra Work 26,085.63 0.00 b. Adjustment Comp. -1,164.47 0.00 3. Materials on Hand 43,951.00 0.00 4. Earned Subject to Retention 2,646,175.66 24,685.20 5. Mobilization 396,000.00 0.00 6. Total Work Completed 2,998,224.66 7. Deductions -3,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,039,175.66 21,685.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,685.20