Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-116-19-07 01-293014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-101-10.7/ .0 Federal Project: ACNH-Q101(66) Progress payment No. 22 Payment period ending: 02-14-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,615,245.39 2,802.40 2.a. Extra Work 136,792.56 17,973.40 b. Adjustment Comp. -1,910.54 468.19 3. Materials on Hand 4. Earned Subject to Retention 3,750,127.41 21,243.99 5. Mobilization 396,000.00 0.00 6. Total Work Completed 4,146,127.41 7. Deductions -24,000.00 -18,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,122,127.41 3,243.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,243.99