Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-303-13-53 01-293014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-101-10.7/ .0 Federal Project: ACNH-Q101(66) Progress payment No. 24 Payment period ending: 02-14-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,620,745.39 5,500.00 2.a. Extra Work 150,664.99 1,984.64 b. Adjustment Comp. -506.43 -508.39 3. Materials on Hand 4. Earned Subject to Retention 3,770,903.95 6,976.25 5. Mobilization 396,000.00 0.00 6. Total Work Completed 4,166,903.95 7. Deductions -2,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,164,903.95 6,976.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,976.25