Dept. of Trans. PROGRESS Serial No. Contract No. 17-171-13-30 01-293024 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 43% Location: Federal Project: 01-MEN-101-42.1/42.1 STP-Q101(295) Progress payment No. 004 Payment period ending: 06-20-17 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 264,157.50 215,701.50 2. a. Extra Work 10,101.53 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -38,239.93 4. Earned Subject to Retention 274,259.03 177,461.57 5. Mobilization 73,857.75 15,549.00 6. Total Work Completed 348,116.78 7. Deductions -38,888.00 -38,888.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 309,228.78 154,122.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,122.57