Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-09-56 01-293144 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 52% 01-DN-199-10.9/11.2 Federal Project: ACBR-P199(31) NH-P199(31) Progress payment No. 07 Payment period ending: 06-20-08 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 767,888.50 33,971.60 2.a. Extra Work 37,479.90 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 805,368.40 33,971.60 5. Mobilization 190,000.00 0.00 6. Total Work Completed 995,368.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 995,368.40 33,971.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,971.60