Dept. of Trans. PROGRESS Serial No. Contract No. 01-057-08-31 01-293504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 45% 01-MEN-101-37.6/39.6 Federal Project: ACST-P101(936) PH-P101(936) Progress payment No. 09 Payment period ending: 02-20-01 PARNUM PAVING INC P O BOX 970 UKIAH CA 95482 Escrow No. 01489 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,619,400.32 23,412.53 2.a. Extra Work 468,825.48 12,660.13 b. Adjustment Comp. 2,833.60 0.00 3. Materials on Hand 63,687.91 0.00 4. Earned Subject to Retention 4,154,747.31 36,072.66 5. Mobilization 555,000.00 0.00 6. Total Work Completed 4,646,059.40 7. Deductions 8. a.Contract Retentions -207,737.37 -1,803.64 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,502,009.94 34,269.02 10. Reduction Amt to Escrow 11. Payment to Escrow 207,730.00 12. Net Pymt. this Estimate 34,269.02