Dept. of Trans. PROGRESS Serial No. Contract No. 02-207-14-17 01-293504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 66% 01-MEN-101-37.6/39.6 Federal Project: ACST-P101(936) PH-P101(936) Progress payment No. 30 Payment period ending: 07-19-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE, CA 950775085 Escrow No. 01489 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,870,514.21 0.00 2.a. Extra Work 5,629,169.54 1,256,470.93 b. Adjustment Comp. 9,028.87 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,508,712.62 1,256,470.93 5. Mobilization 555,000.00 0.00 6. Total Work Completed 11,063,712.62 7. Deductions -877.50 0.00 8. a.Contract Retentions -525,435.63 -62,823.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,537,399.49 1,193,647.38 10. Reduction Amt to Escrow 11. Payment to Escrow 525,430.00 12. Net Pymt. this Estimate 1,193,647.38