Dept. of Trans. PROGRESS Serial No. Contract No. 12-356-10-56 01-296104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 87% 01-HUM-101-89.3/R90.2 Federal Project: ACNH-X023(33) ACBH-X023(33) NH-X023(33) Progress payment No. 51 Payment period ending: 12-19-12 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,896,127.50 312,680.00 2.a. Extra Work 1,516,781.68 79,638.26 b. Adjustment Comp. -10,433.27 -50,893.41 3. Materials on Hand 4. Earned Subject to Retention 36,402,475.91 341,424.85 5. Mobilization 3,333,333.00 0.00 6. Total Work Completed 39,735,808.91 7. Deductions -15,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,720,808.91 336,424.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 336,424.85