Dept. of Trans. PROGRESS Serial No. Contract No. 03-199-16-02 01-296704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 14% 01-HUM-255-0.2/1.9 Federal Project: NONE Progress payment No. 05 Payment period ending: 07-18-03 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 02095 Total Estimate This Estimate 1. Contract Itms Without Mobil. 447,408.80 104,355.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 10,165.80 6,203.95 4. Earned Subject to Retention 457,574.60 110,558.95 5. Mobilization 6. Total Work Completed 447,408.80 7. Deductions 8. a.Contract Retentions -45,757.46 -11,055.89 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 411,817.14 99,503.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 99,503.06