Dept. of Trans. PROGRESS Serial No. Contract No. 04-265-10-38 01-296704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 56% 01-HUM-255-0.2/1.9 Federal Project: NONE Progress payment No. 19 Payment period ending: 09-20-04 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 02095 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,539,208.23 485,803.25 2.a. Extra Work 456,001.58 61,272.82 b. Adjustment Comp. 312,349.09 1,612.60 3. Materials on Hand 179,893.48 -38,285.92 4. Earned Subject to Retention 12,487,452.38 510,402.75 5. Mobilization 2,115,000.00 0.00 6. Total Work Completed 14,422,558.90 7. Deductions 0.00 1,000.00 8. a.Contract Retentions -624,372.62 -25,520.14 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,978,079.76 485,882.61 10. Reduction Amt to Escrow 11. Payment to Escrow 624,370.00 12. Net Pymt. this Estimate 485,882.61