Dept. of Trans. PROGRESS Serial No. Contract No. 05-300-08-59 01-296704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-HUM-255-0.2/1.9 Federal Project: NONE Progress payment No. 32 Payment period ending: 10-20-05 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 02095 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,544,050.78 439,092.85 2.a. Extra Work 621,648.12 8,163.08 b. Adjustment Comp. 353,169.17 155.70 3. Materials on Hand 19,208.69 -35,248.35 4. Earned Subject to Retention 19,538,076.76 412,163.28 5. Mobilization 2,115,000.00 0.00 6. Total Work Completed 21,633,868.07 7. Deductions -5,000.00 -4,000.00 8. a.Contract Retentions -976,903.84 -20,608.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,671,172.92 387,555.11 10. Reduction Amt to Escrow 11. Payment to Escrow 976,900.00 12. Net Pymt. this Estimate 387,555.11