Dept. of Trans. PROGRESS Serial No. Contract No. 21-116-12-59 01-2982U4 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 35% Location: Federal Project: 01-LAK-29-28.5/31.6 ACNH-P029(148) Progress payment No. 016 Payment period ending: 04-20-21 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,625,855.21 1,981,310.98 2. a. Extra Work 861,781.56 51,996.59 b. Adustment Comp. 566,238.34 0.00 3. Materials on Hand 144,907.91 -2,023.22 4. Earned Subject to Retention 20,198,783.02 2,031,284.35 5. Mobilization 5,035,000.00 0.00 6. Total Work Completed 25,088,875.11 7. Deductions -18,000.00 50,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,215,783.02 2,081,284.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,081,284.35