Dept. of Trans. PROGRESS Serial No. Contract No. 03-052-06-41 01-301704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 67% 01-MEN-101-5.7/9.2 Federal Project: ACNH-P101(969) Progress payment No. 20 Payment period ending: 02-20-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE, CA 950775085 Escrow No. 01810 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,873,891.13 1,000.00 2.a. Extra Work 626,613.12 25,129.76 b. Adjustment Comp. 56,454.20 -2,838.40 3. Materials on Hand 29,903.10 0.00 4. Earned Subject to Retention 11,586,861.55 23,291.36 5. Mobilization 1,453,000.00 0.00 6. Total Work Completed 13,009,958.45 7. Deductions -24,600.00 10,000.00 8. a.Contract Retentions -579,343.08 -1,164.57 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,435,918.47 32,126.79 10. Reduction Amt to Escrow 11. Payment to Escrow 579,340.00 12. Net Pymt. this Estimate 32,126.79