Dept. of Trans. PROGRESS Serial No. Contract No. 03-356-11-19 01-301704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 100% 01-MEN-101-5.7/9.2 Federal Project: ACNH-P101(969) Progress payment No. 31 Payment period ending: 12-19-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE, CA 950775085 Escrow No. 01810 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,556,661.07 21,600.00 2.a. Extra Work 2,933,130.94 623,748.01 b. Adjustment Comp. 172,168.12 -9,657.62 3. Materials on Hand 4. Earned Subject to Retention 16,661,960.13 635,690.39 5. Mobilization 1,453,000.00 0.00 6. Total Work Completed 18,114,960.13 7. Deductions -302,714.85 -159,359.79 8. a.Contract Retentions -833,098.01 -31,784.52 b. Unsatisfactory Prog. -82,792.22 -31,784.52 c. Reduction after 95% Comp. 9. Total pay to Contractor 16,896,355.05 412,761.56 10. Reduction Amt to Escrow 11. Payment to Escrow 833,090.00 12. Net Pymt. this Estimate 412,761.56