Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 04-155-09-38 01-301704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 75% 01-MEN-101-5.7/9.2 Federal Project: ACNH-P101(969) Progress payment No. 37 Payment period ending: 05-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE, CA 950775085 Escrow No. 01810 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,751,656.94 96,163.39 2.a. Extra Work 4,860,717.47 27,339.09 b. Adjustment Comp. 215,019.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 18,827,393.63 123,502.48 5. Mobilization 1,453,000.00 0.00 6. Total Work Completed 20,280,393.63 7. Deductions -129,599.56 0.00 8. a.Contract Retentions -941,369.68 -6,175.12 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,209,424.39 117,327.36 10. Reduction Amt to Escrow 11. Payment to Escrow 941,360.00 12. Net Pymt. this Estimate 117,327.36