Dept. of Trans. PROGRESS Serial No. Contract No. 12-325-11-02 01-310104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 29% 01-MEN-1-33.4/33.9 Federal Project: BRST-POO1(559) P-P001(559) Progress payment No. 08 Payment period ending: 11-20-12 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,169,167.07 246,120.70 2.a. Extra Work 123,164.07 28,522.65 b. Adjustment Comp. 21,405.00 0.00 3. Materials on Hand 85,752.36 0.00 4. Earned Subject to Retention 2,399,488.50 274,643.35 5. Mobilization 855,000.00 0.00 6. Total Work Completed 3,168,736.14 7. Deductions -2,630.00 15,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,251,858.50 289,643.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 289,643.35