Dept. of Trans. PROGRESS Serial No. Contract No. 13-052-14-08 01-310104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 39% 01-MEN-1-33.4/33.9 Federal Project: BRST-POO1(559) P-P001(559) Progress payment No. 11 Payment period ending: 02-20-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,919,951.81 317,787.88 2.a. Extra Work 151,038.07 0.00 b. Adjustment Comp. 21,405.00 0.00 3. Materials on Hand 76,993.20 -23,298.36 4. Earned Subject to Retention 3,169,388.08 294,489.52 5. Mobilization 855,000.00 0.00 6. Total Work Completed 3,947,394.88 7. Deductions -2,630.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,021,758.08 294,489.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 294,489.52