Dept. of Trans. PROGRESS Serial No. Contract No. 13-113-09-04 01-310104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 46% 01-MEN-1-33.4/33.9 Federal Project: BRST-POO1(559) P-P001(559) Progress payment No. 13 Payment period ending: 04-18-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,007,279.41 569,279.34 2.a. Extra Work 181,987.69 13,528.75 b. Adjustment Comp. -16,627.40 -38,032.40 3. Materials on Hand 4. Earned Subject to Retention 4,172,639.70 544,775.69 5. Mobilization 855,000.00 0.00 6. Total Work Completed 5,027,639.70 7. Deductions -2,630.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,025,009.70 544,775.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 544,775.69