Dept. of Trans. PROGRESS Serial No. Contract No. 13-203-13-28 01-310104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 57% 01-MEN-1-33.4/33.9 Federal Project: BRST-POO1(559) P-P001(559) Progress payment No. 16 Payment period ending: 07-18-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,048,072.49 183,605.00 2.a. Extra Work 181,987.69 0.00 b. Adjustment Comp. -16,627.40 0.00 3. Materials on Hand 193,616.69 193,616.69 4. Earned Subject to Retention 5,407,049.47 377,221.69 5. Mobilization 900,000.00 0.00 6. Total Work Completed 6,113,432.78 7. Deductions -2,630.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,304,419.47 377,221.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 377,221.69