Dept. of Trans. PROGRESS Serial No. Contract No. 13-235-09-12 01-310104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 61% 01-MEN-1-33.4/33.9 Federal Project: BRST-POO1(559) P-P001(559) Progress payment No. 17 Payment period ending: 08-20-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,303,881.39 255,808.90 2.a. Extra Work 181,987.69 0.00 b. Adjustment Comp. -16,627.40 0.00 3. Materials on Hand 193,616.69 0.00 4. Earned Subject to Retention 5,662,858.37 255,808.90 5. Mobilization 900,000.00 0.00 6. Total Work Completed 6,369,241.68 7. Deductions -2,630.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,560,228.37 255,808.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 255,808.90