Dept. of Trans. PROGRESS Serial No. Contract No. 14-021-14-02 01-310104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 77% 01-MEN-1-33.4/33.9 Federal Project: BRST-POO1(559) P-P001(559) Progress payment No. 23 Payment period ending: 01-17-14 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,210,455.61 164,315.00 2.a. Extra Work 326,158.89 5,854.53 b. Adjustment Comp. 73,166.90 30,255.00 3. Materials on Hand 108,924.14 -84,692.55 4. Earned Subject to Retention 7,718,705.54 115,731.98 5. Mobilization 900,000.00 0.00 6. Total Work Completed 8,509,781.40 7. Deductions -2,630.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,616,075.54 115,731.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,731.98