Dept. of Trans. PROGRESS Serial No. Contract No. 14-052-09-23 01-310104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 81% 01-MEN-1-33.4/33.9 Federal Project: BRST-POO1(559) P-P001(559) Progress payment No. 25 Payment period ending: 02-20-14 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,398,080.61 147,305.00 2.a. Extra Work 413,288.50 8,274.16 b. Adjustment Comp. 73,166.90 0.00 3. Materials on Hand 103,477.93 -5,446.21 4. Earned Subject to Retention 7,988,013.94 150,132.95 5. Mobilization 900,000.00 0.00 6. Total Work Completed 8,784,536.01 7. Deductions -12,630.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,875,383.94 140,132.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,132.95