Dept. of Trans. PROGRESS Serial No. Contract No. 14-080-10-16 01-310104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 83% 01-MEN-1-33.4/33.9 Federal Project: BRST-POO1(559) P-P001(559) Progress payment No. 26 Payment period ending: 03-20-14 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,704,447.61 306,367.00 2.a. Extra Work 548,253.47 134,964.97 b. Adjustment Comp. 73,166.90 0.00 3. Materials on Hand 0.00 -103,477.93 4. Earned Subject to Retention 8,325,867.98 337,854.04 5. Mobilization 900,000.00 0.00 6. Total Work Completed 9,225,867.98 7. Deductions -12,630.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,213,237.98 337,854.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 337,854.04