Dept. of Trans. PROGRESS Serial No. Contract No. 03-294-15-00 01-310404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 100% 01-HUM-283-0.1/0.4 Federal Project: STP-S283(1) ACBH-S283(1) Progress payment No. 24 Payment period ending: 10-20-03 F D THOMAS INC P O BOX 4663 MEDFORD OR 97501 Escrow No. 01853 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,124,810.91 82,206.73 2.a. Extra Work 239,473.10 0.00 b. Adjustment Comp. -151,236.37 -16,477.44 3. Materials on Hand 4. Earned Subject to Retention 4,213,047.64 65,729.29 5. Mobilization 194,000.00 0.00 6. Total Work Completed 4,407,047.64 7. Deductions 8. a.Contract Retentions -210,652.38 -3,286.46 b. Unsatisfactory Prog. -51,060.87 -3,286.46 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,145,334.39 59,156.37 10. Reduction Amt to Escrow 11. Payment to Escrow 210,650.00 12. Net Pymt. this Estimate 59,156.37