Dept. of Trans. PROGRESS Serial No. Contract No. 09-168-14-24 01-3116U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 94% 01-MEN-253-0.5/3.5 Federal Project: ACST-X045(20) P-X045(20) ACBH-X045(20) Progress payment No. 18 Payment period ending: 06-19-09 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,080,234.42 28,990.25 2.a. Extra Work 119,031.55 0.00 b. Adjustment Comp. -4,782.93 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,194,483.04 28,990.25 5. Mobilization 375,000.00 0.00 6. Total Work Completed 3,569,483.04 7. Deductions -81,111.31 -7,247.56 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,488,371.73 21,742.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,742.69