Dept. of Trans. PROGRESS Serial No. Contract No. 10-083-11-15 01-3116U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 100% 01-MEN-253-0.5/3.5 Federal Project: ACST-X045(20) P-X045(20) ACBH-X045(20) Progress payment No. 23 Payment period ending: 03-22-10 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,266,008.22 0.00 2.a. Extra Work 267,985.02 35,961.89 b. Adjustment Comp. -8,632.93 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,525,360.31 35,961.89 5. Mobilization 375,000.00 0.00 6. Total Work Completed 3,900,360.31 7. Deductions -93,685.04 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,806,675.27 35,961.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,961.89