Dept. of Trans. PROGRESS Serial No. Contract No. 05-207-06-56 01-311714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 5% 01-DN-169-2.3/2.9 Federal Project: ACBR-S169(4) STP-S169(4) Progress payment No. 07 Payment period ending: 07-20-05 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 270,569.00 220,333.00 2.a. Extra Work 74,321.82 14,792.86 b. Adjustment Comp. -5,000.00 0.00 3. Materials on Hand 493,487.40 -200.00 4. Earned Subject to Retention 833,378.22 234,925.86 5. Mobilization 329,650.00 69,400.00 6. Total Work Completed 669,540.82 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,161,028.22 302,325.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 302,325.86