Dept. of Trans. PROGRESS Serial No. Contract No. 05-236-16-19 01-311714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 13% 01-DN-169-2.3/2.9 Federal Project: ACBR-S169(4) STP-S169(4) Progress payment No. 08 Payment period ending: 08-19-05 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 752,382.61 481,813.61 2.a. Extra Work 77,929.40 3,607.58 b. Adjustment Comp. -5,000.00 0.00 3. Materials on Hand 278,737.40 -214,750.00 4. Earned Subject to Retention 1,104,049.41 270,671.19 5. Mobilization 329,650.00 0.00 6. Total Work Completed 1,154,962.01 7. Deductions -9,523.83 -7,523.83 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,424,175.58 263,147.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 263,147.36